GEOLOGICAL SOCIETY OF THE PHILIPPINES

 

Tiwi Geothermal Field, Philippines: 30 years of Commercial Operation

 

Anthony J. Menzies, Larry B. Villaseńor and Eugene G. Sunio

Chevron Geothermal Philippines Holdings, Inc, 14th Floor 6750 Building, Ayala Avenue, Makati City, Philippines

 

Abstract

 

The Service Contract for the exploration and development of the Tiwi geothermal resource was executed in 1971 between Chevron Geothermal Philippines Holdings, Inc (CGPHI) and the National Power Corporation of the Philippines.  The deep discovery well, Naglagbong-1, was completed in June 1972 and demonstrated the commercial viability of the resource.  By May 1979, 45 wells had been drilled and the first 55MWe turbine-generator unit had started commercial operation.  This was followed by a second 55MWe unit in August 1979 and by April 1982 the installed capacity had reached 330MWe, with six 55MWe turbines located in three power plants.  This was a very aggressive development schedule but was considered necessary due to the Philippines’ heavy dependence on imported oil and the oil price shocks of the 1970’s.  In 2004-05, four of the units were rehabilitated and the base installed capacity was re-rated to 234MWe, with the retirement of Unit 4 in 2000 and the designation of Unit 3 as a stand-by unit in 2005.

 

Since the start of commercial operation, gross generation at Tiwi has averaged 157MWe and 40.6TWe-hrs of electricity has been provided to the Luzon grid, saving the Philippines from importing 80.6 million barrels of oil (or equivalent fuel).  This level of generation is in line with early assessments of Tiwi’s long-term production capacity.  Generation in recent years has been affected by steam supply limitations, power plant availability and the introduction of a competitive wholesale electricity market (WESM) which initially resulted in the units being used more as “load following” rather than “base load” plants, although this situation did improve in 2008.

 

Management of the Tiwi resource over the past 30 years has been a challenge, with specific sectors of the field being affected at various times by: massive meteoric water influx; injection breakthrough; steep reservoir pressure declines; high non-condensible gas concentrations; significant enthalpy changes; and production of corrosive fluids (both sulfuric and hydrochloric acids).  These difficulties have been overcome or managed by instituting a number of technical and operational changes.  In 2008 the decline in steam supply was minimal, suggesting that the present capacity of ≈190MWe equivalent (based on design consumption of 2.25 kg/s steam per MWe) is reasonably sustainable, based on the existing reservoir production/injection strategy.  Two new production wells were drilled in late 2008 and early indications are that these wells will assist in maintaining production at the present overall capacity and may also suggest the existence of additional reserves that could increase or extend the capacity in future years, if considered economically viable.  CGPHI looks forward to many more years of continued operation of this high-quality but challenging geothermal resource.

 

 
To get the whole report , please call (633-9025) or email us: info@geolsocphil.org 
 

Geological Society of the Philippines

Unit 250, 2nd Floor, Cityland Pioneer,

128 Pioneer Street, Mandaluyong City, Philippines

Tel: +(63-2) 633-9025